Lafayette Area 21

Lafayette Area 21

Lafayette, IN

Lafayette Area 21

HWC worked with the City of Lafayette to complete the Service Area 21 – Sewer & Water Utility Master Plan Project. Service Area 21 refers to a 4,000-acre area outside the corporate limits of Lafayette.

A crossing of Wildcat Creek and I-65 was evaluated as part of this study. Connecting the water service to Lafayette’s dual water pressure zone system was also evaluated.

The area is largely agricultural but includes several housing developments and the potential for commercial development. As such, there was a need for water and wastewater utilities to service the area.

The final plan included the phased extension of water and sewer services to the area. Future phases can extend these utilities throughout the entire service area and consist of a new well field for supplemental water supply due to the impacts of the proposed Hoosier Heartland corridor.

The estimated construction costs for both phases developed in the plan is $5.8 million. Design and construction management of Phase I were completed by HWC with construction inspected in 2020.

Attica Water System Improvements

Attica Water System Improvements

Attica, IN

Water System Improvements

HWC provided planning, design, and construction inspection services on this water system improvement project, which included a system evaluation for a city of 3,600 citizens.

Improvements included a 500,000 gallon elevated storage tank, a pumping station upgrade, a distribution supply system upgrade (20,000 LF of 6”, 8”, & 12” mains and appurtenances), and upgrades implemented a two-zone pressure system utilizing the new elevated tank and an existing ground storage reservoir. The total construction cost was $2.1M.

Princeton Water Treatment Facility Improvements

Princeton Water Treatment Facility Improvements

Princeton, IN

Water Treatment Facility Improvements

HWC completed an SRF Preliminary Engineering Report for the City’s water treatment facility.  Improvements to the capacity and replacement of antiquated equipment and processes included:

  • 3 new 1,000 gallon per day aerators and a 3rd aerator/detention basin
  • Replacement treatment pumps with variable frequency drives
  • New 500,000 gallon ground storage tank and new high service pumping station
  • New filter backwash waste holding basin to eliminate the existing process of recycling backwash wastewater
  • New SCADA controls system for improved efficiency and reliable supply 

Project Highlights:

  • One million gallons of additional water storage for the system
  • Increased capacity of the plant to 3.0 MGD
  • Replacement of existing high service pumps with two sets of pumps to reduce the high pressure required of the existing pumps which conveyed flow through the filters and into the system
  • Modifications at the treatment plant to replace antiquated equipment and allow for future expansion if necessary
  • HWC completed all facility evaluations, planning, design, bidding, and construction management phases
  • Construction cost of $4.5 million (funded by an SRF loan and an IOCRA DR II grant)
  • Construction completed in 2011

Brazil Water System Improvements

Brazil Water System Improvements

Brazil, IN

Water System Improvements

HWC provided planning, design, bidding, and construction management phases for this water system improvement project.  The improvements to the system were determined through an SRF Preliminary Engineering Report (PER) completed by HWC in 2009. The items of concern that were evaluated in the PER were a reduction in well capacity, the deteriorating condition of an existing elevated tank, inadequate flow provided near the I-70/SR-59 interchange, the lack of centralized control/monitoring abilities of the system, areas with old and undersized water mains, and sections of aging hydrants and meters.

Project Highlights:

 

  • New 700 gallon per day well in the existing wellfield
  • Replacement 750,000 gallon elevated water tank in the City
  • New 250,000 gallon elevated water tank near the I-70/SR-59 interchange
  • A booster station with variable frequency drives for the 250,000 gallon tank, along with a backup generator
  • New SCADA system at the water treatment plant to monitor/control the plant, elevated tanks, wellfield, and booster station
  • Replacement of 23,000 LF of water main, 100 hydrants, and 1,000 meters
  • Project bid in Spring 2010 in 5 divisions
  • Construction cost – $6.0M (funded by an SRF loan and an IOCRA DR II grant
  • Construction completed in December 2011

Seelyville Water Supply Wells, Treatment Plant and Storage Facilities

Seelyville Water Supply Wells, Treatment Plant and Storage Facilities

Seelyville, IN

Water Supply Wells, Treatment Plant, and Storage Facilities

 

HWC provided planning, permitting, design, and construction administration services for the construction of a new Water Treatment Facility and new Distribution and Storage System for the Seelyville Waterworks Utility in eastern Vigo County, Indiana.

Phase I of the project included the development of a new water supply well field, a new water treatment facility, new water transmission mains and storage improvements.

Phase II of the new system provided necessary flow and pressure to approximately 250 homes on the western extremity of the Seelyville system via a new isolated pressure zone served by a new 500,000 gallon tank and booster station.

Phase III included analysis and design of the improvements for the treatment facility to serve approximately 400 new customers in an unserved township northeast of the utility. The preliminary study and design for this project included modifications for additional capacity for the filters and chemical feed systems.